project brief

This project involved the development of a railway balloon siding at the new back of port facility, Saldanha Dry Bulk Terminal, a critical component of South Africa's bulk export infrastructure.

innovative process

Scope of Work

  • Construction of a 2.2km railway balloon siding
  • Comprehensive earthworks
  • Installation of 200m of track slab
  • Implementation under the NEC3 ECC framework

ACRE’s Role

  • Project and Contract Management for the Principal Contractor (W.O. Trackworks (Pty) Ltd)
  • Appointment as the responsible person under Section 16(2) of the Occupational Health and Safety Act
  • Development of risk assessments and safe working procedures
  • Compliance monitoring and enforcement
  • Project documentation and reporting

the result

The balloon siding development, able to accept 100 tons per wagon trains, enhanced Transnet’s operational flexibility and efficiency at the Port of Saldanha export terminal, reducing cycle times and improving throughput capacity for bulk materials.